|
|
||||||||
![]() |
|
|||||||
|
|
||||||||
|
|
|
|||||||
|
OSHA takes perc off regulatory agenda
Plans to devise a new workplace
exposure level have been withdrawn
OSHA has called a halt in its 13-year
effort to establish lower standards for workplace exposure to
perchloroethylene.
A brief announcement in OSHA’s
semi-annual regulatory agenda published last month said the
agency is withdrawing its plans to re-evaluate perc “at
this time due to resource constraints and other priorities.”
The planned re-evaluation had been on the
agenda since 1996 when OSHA put perc on a list of 20 chemicals
to examine for possible revision of maximum workplace exposure
levels.
Other than “resource constraints and
other priorities,” there was no other explanation from
OSHA for removing perc from the agenda now. However, Bob
Wright, an OSHA public affairs officer noted that perc could be
placed back on the agenda at some time in the future. A number
of other items were removed from the regulatory agenda this
fall for similar reasons.
For perc, the workplace exposure limits
remain where they were in 1988 when OSHA made its first attempt
at revising them. At that time, OSHA proposed dropping the
8-hour time weighted exposure from 100 parts per million (ppm)
to 25 parts per million as part of a wholesale revision that
involved several hundred other substances.
That action was overturned by the Eleventh
Circuit Court of Appeals in July 1992 in a ruling that stated
OSHA needed to show a scientific basis for setting new levels
of each chemical. At the time, the International Fabricare
Institute, which had joined the suit against OSHA, said that a
level of 50 ppm would be sufficient to protect workers in perc
plants. Labor groups, however, were also suing OSHA, arguing
that the level should be even lower than 25 ppm.
After the court ruling, the previous 100
ppm level was reinstated. In 1996, OSHA again stated its
intention to lower the perc exposure level, but despite fears
among some in the industry that OSHA might reduce the level to
below 10 ppm, little has taken place over the past five years.
OSHA heard from industry representatives
at a meeting in 1996 on the issue. At that meeting, the
Neighborhood Cleaners Association told OSHA that the 100 ppm
level was too high but that a 50 ppm level would be realistic.
The following year, IFI announced that a
revived exposure level for perc would be delayed at least until
1998, citing the complexities that OSHA faced in the
rule-making process which required OSHA to perform four
substantial legal analyses. OSHA first would need to identify
that a risk exists, that the risk is substantial and that a new
exposure limit would reduce that risk. OSHA also would need to
show that the means to reduce the risk are “technically
and economically feasible” for an industry.
Later that year, OSHA met with a number of
parties interested in the issue, including, IFI, NCA, the
Textile Care Allied Trades Association, the Fabricare
Legislative and Regulatory Education organization, the Center
for Emissions Control, Greenpeace and advocates of substitute
technologies. At that time it was said that the process of
setting a new PEL for perc could take one to two years to
complete.
In 1998, OSHA announced that perc would
not be among the first group of chemicals to get new exposure
standards.
Although the possibility of new, lower
exposure limits has lurked in the background over the past few
years, there has been no further word from OSHA that it was
ready to take action. Pat Williams, IFI’s government
relations director, said OSHA officials met with IFI about a
year ago to discuss possible future directions, but nothing had
been heard from the agency on the issue since then.
Thus, for the foreseeable future, OSHA’s
permissible exposure levels remain where they were in 1988. The
time weighted exposure, which is the average as measured over
an eight-hour day, is 100 ppm. The ceiling limit, which can’t
be exceeded except for peak exposures, is 200 ppm; and the
maximum peak exposure, which is the ceiling limit for an
eight-hour shift, limited to five minutes in any three-hour
period, is 300 ppm.
It should be noted that more
stringent standards have been adopted by some states and that a
25 ppm limit has been advocated by both the American Conference
of Governmental Industrial Hygienists (ACGIH). Dow’s
product literature and MSDS for perc also advise a 25 ppm
maximum exposure level.
Although OSHA has been unable to revise
its exposure levels for perc, changes within the industry may
have largely achieved the same results. Last year, Dow noted
that average worker exposure from third, fourth, and fifth
generation equipment is typically below 10 ppm. Exposure from
first generation equipment averages about 37 ppm, however.
Cleaners can’t trust their noses to
tell them when perc vapor levels are getting too high. For most
people, the odor threshold is in the range of 40-50 ppm. For
some with sensitive olfactory nerves, it can be as low as 5
ppm. But for people who are regularly exposed to the odor, the
threshold is likely to be much higher.
|
|
|||||||
|
|
||||||||
|
|
||||||||
|
|
|
|
|
|
|
|
|
|
